Client:
Date Started:
Date Completed:
Location:
About Project
The intent of the Expo Aspect Standardization Project was to bring the entire Expo Line (Expo Line 1 and Expo Line 2) aspects to to LACMTA’s new aspect standards. The project consisted of 19 Interlocking and Intermediate locations that required software and hardware modifications.
Project Scope, Successes
- S004A – Maple
- S006A – Venice
- S008B – Junction
- S008C – Junction
- S010 – 22nd C1
- S010 – 22nd C2
- S020 – Jefferson
- S025 – USC Expo
- S030 – Vermont
- S040 – Crenshaw
- S046 – Hauser
- S050B – La Cieneg
- S060A – National
- S060C – National
- S065 – Culver City
Pacific Railway Enterprises, Inc. (PRE) was responsible for Preliminary Software Design, Final Software Design, Delivery of EEPROMS, Field Support, and As-Built Documentation for all train control locations required on Expo Line Phase 1 (S004A through S065 inclusive).
PRE was responsible for the software modifications to Expo Line 1 at the following locations:
PRE back checked Expo Line 2 software design done by others.
PRE was also responsible for developing all test documentation and In-service testing.
All software modifications have been made, test plans developed and 6 locations have been placed in-service (by others).
Project Highlights
- Preliminary Software Design
- Final Software Design
- Delivery of EEPROMS
- Field Support
- As-Built Documentation